TRANSFORMERS
1.
Feralloys Machadodorp Plant (Engineers -
Bateman Titaco)
Supply, transport to site and installation of 4 x 18 MVA, 33 / 0,23-0,43 kV
single-phase furnace transfomers.
2.
Zimasco (Zimbabwe) (Engineers - Bateman
Titaco)
Supply, transport to site and installation of 4 x 10 MVA, 33 / 11 /
0,2-0,376 kV single-phase furnace transformers.
3.
Anglo Platinum - Waterval Slag Cleaning
furnace
Supply, transport to site and installation of 4 x 10 MVA, 6,6 / 0,14-0,36
kV single-phase furnace transformers.
4.
Anglo Platinum – Polokwane Smelter
Supply, transport to site, erection and commissioning of 4 x 56 MVA, 33 /
0,29-0,8 kV single-phase furnace transformers.
5.
Saldanha Steel
Supply, transport to site and installation of 1 x 138 MVA, 33 / 0,59-1,039 kV
three-phase furnace transformer.
6.
Sentrachem - Newcastle
Supply, transport to site and installation of 1 x 38 MVA, 132 / 0,086-0,3
kV three-phase furnace transformer.
7.
Assmang – Machadodorp
Supply, transport to site and installation of 2 x 33 MVA, 33 / 0,12-0,37 kV
three-phase furnace transformer.
8.
Scaw Metals
Supply, transport to site and installation of 2 x 7,9 MVA, 6,6 / 0.11-0.275
kV three-phase furnace transformer.
9.
Ferrometals – Witbank (Engineers –
Bateman Titaco)
Supply, transport and delivery to site 1 x 12,5 MVA, 33 / 6,6 kV
three-phase power transformer.
10.
Marqott Power Projects
Supply and delivery to site 1 x 10 MVA, 60 / 15 kV and 1 x 5 MVA, 15 / 6 kV
three-phase power transformers.
11.
Tubatse Ferrochrome
Supply, transport to site and installation 1 x 12,33 MVA, 33 / 0,4-0,2 kV
three-phase furnace transformer.
12.
ISCOR – Vereeniging
Supply, transport to site, installation and commissioning 1 x 75 / 84 MVA,
33 / 0,9-0,509 kV single-phase furnace transformer.
13.
Xstrata – Lion Project
Supply, transport to site, installation and commissioning 7 x 21 MVA, 33 /
0,462-0,230 kV single-phase furnace transformers.
14.
Davsteel
Supply, transport to site, installation and commissioning 1 x 65 / 78 MVA,
33 / 0,9-0,46 kV three -phase furnace transformer.
15. Tata
Ferrochrome Under manufacture -
7 x 12,67 MVA, 33/0,37-0,19 kV
16. Techint
for Assmang Cato Ridge Under manufacture - 3 x 12 MVA, 33/0,28- 0,1 kV
17. Zimasco,
Zimbabwe Under manufacture -
3 x 10 MVA, 33/0,189-0,376 kV
CONSULTING DESIGN AND PROJECT
MANAGEMENT
MINING
18.
Blyvooruitzicht gold mine
Project management : 1 x 5,5 MVAr, 22 kV power factor correction bank; 1 x
3,5 MVAr, 22 kV power factor correction bank; 2 x 2 MVAr, 6,6 kV power
factor correction banks; 2 x 3,5 MVAr, 6,6 kV power factor correction
banks.
19.
Doornfontein gold mine
Tariff impact study and electrical system study, PFC design,
specification and project management : 2 x 5 MVAr, 5th harmonic filter
banks; 2 x 3 MVAr, 5th harmonic filter banks; 1 x 3 MVAr, power factor
correction bank.
|
|

|
20.
Forzando Mine (AVMIN)
Feasibility study in respect of power factor correction/harmonic filtering
requirements.
21.
Beeshoek Mine (AVMIN)
Electrical system study in respect of the effectiveness of existing PFC,
design and specification of additional PFC requirements, project management
: upgrading of an existing 22 kV 2,2 MVAr capacitor bank to 4,8 MVAr 5th
harmonic filter.
22.
Blackrock Mine (AVMIN)
Electrical system study in respect of the effectiveness of existing PFC,
design and specification of additional PFC requirements, project management
: upgrading of the existing 22 kV capacitor bank installation.
23.
Afrikaner Lease Gold Mine
Electrical system study, 6,6 kV PFC design and specification.
24.
Kinross Gold Mine
Electrical system study in respect of the effectiveness of existing
PFC/harmonic filter installation consisting of six 6,6 kV harmonic filter
banks, together with recommendations to improve and optimise this PFC
installation.
25.
Thabazimbi Iron Ore
(Buffelshoek)
Electrical system study in respect of 22 kV PFC requirements and PFC
design/specification.
26.
Thabazimbi Iron Ore
Investigation into problems experienced with failure and mal-operation of LV reactive power
compensation on P&H 2300 shovels, together with recommendations in
respect of remedial measures to improve the shovel supply voltage
regulation.
27.
Nkomati Mine (AVMIN)
Electrical system study, PFC design and specification, project management :
one 22 kV 1,8 MVAr capacitor bank, upgradeable to 5,4 MVAr 5th harmonic
filter.
28.
Bikita Zimbabwe
Project management : one 6,6 kV 900 kVAr pole mounted capacitor bank.
29.
Buffelsfontein Gold Mine
Electrical system study, 6,6 kV PFC design and specification.
30.
East Rand Gold and Uranium Company (Ergo)
Nightsave tariff impact study. Electrical system study, 11 kV PFC design
and specification, project management : 2 x 2,2 MVAr capacitor banks; 3 x
2,2 MVAr capacitor banks; 1 x 3,6 MVAr capacitor bank; 1 x 2,7 MVAr 5th
harmonic filter bank; 1 x 7,2 MVAr 5th harmonic filter bank.
31.
St
Helena Gold Mine
Nightsave tariff impact study. Electrical system study, 6,6 kV PFC design
and specification.
32.
J.R. Mines
Electrical system study, 6,6 kV PFC design and specification.
33.
Arnot Colliery
Megaflex tariff impact study. Electrical system study to determine the
effectiveness of existing 6,6 kV PFC together recommendations in respect of
measures to optimise the PFC installations.
34.
Assmang - Beeshoek Mine
Megaflex tariff impact study and evaluation of the effectiveness of
existing 22 kV PFC. Recommendations in respect of PFC optimisation, tariffs
and associated savings, together with the potential increase in savings
resulting from load shifting.
35.
Assmang - Blackrock Mine
Megaflex tariff impact study and evaluation of the effectiveness of
existing 22 kV PFC. Recommendations in respect of tariffs and associated
savings, PFC optimisation and savings resulting from potential load
shifting, together with increased savings following planned load growth.
36.
Anglo Platinum - Union Section
Megaflex tariff impact study and evaluation of the effectiveness of
existing 11 kV PFC. Recommendations in respect of tariffs and associated
savings.
37.
Anglo Operations - Black
Mountain No.2 Shaft
Greenfield study
: Determination of the predicted shaft load demand and power factor during
typical mining operations. Design and specification of required 6,6 kV
PFC/harmonic filters to correct for the Shaft load and to provide harmonic
filtration for the Rock and Man Winders.
38.
Phalabora Mining Company
Design of remedial measures for, and improvements to, the PMC Substation
reticulation network, in order to ensure the network has sufficient
capacity to provide an adequate electrical supply for the future load
requirements, for both normal and contingency system operation.
39.
Anglo American Corporation - Konkola
Copper Mines (Zambia)
Power factor correction scheme study and equipment technical specification
for the Konkola, Nchanga and Nampundwe Copper Mines.
40.
Anglo American Corporation - Smelter
Company (Zambia)
Power factor correction scheme study and equipment technical specification.
41.
Anglo American Corporation - Konkola
Copper Mines (Zambia)
Detailed and comprehensive protection coordination study of the complete
electrical networks at Nchanga, Konkola and Nampundwe mines and Smelter Co.
42.
Tati Nickel Mine (Botswana)
Comprehensive electrical system study for the overall new project,
including load flow and fault level studies, 11 kV and 3,3 kV motor
starting studies, design check of power factor correction already
specified.
43.
Driefontein Mine - Goldfields of SA
System evaluation of the effectiveness of existing 6,6 kV PFC at the East
2#, West 5# and West 6#. Recommendations in respect of PFC optimisation and
associated tariff savings, implementation of the proposed recommendations.
44.
Driefontein Mine West Gold Plant -
Goldfields of SA
System evaluation of the capability of the Eskom 6,6 kV supply arrangement
for planned load growth together with the effectiveness of existing 6,6 kV
PFC. Recommendations in respect of PFC optimisation, implementation of the
proposed recommendations.
45.
Assmang - Beeshoek Mine
Installation of radio linked energy management system.
46.
President Steyn No.3 Shaft
Design and specification of 6,6 kV PFC and harmonic filter installation.
Project management : 3 MVAr 5th harmonic filter bank; 2 MVAr capacitor
bank.
47.
BCL Mine (Botswana)
Comprehensive system study of the capability of the existing 220/66/11 kV
supply arrangement to provide an adequate capacity for existing and future
2006 mine loading. Recommendations in respect of remedial measures for, and
improvements to, the BCL 220/66/11 kV supply reticulation network, in order
to ensure the network has sufficient capacity to provide an adequate
electrical supply for the future load requirements, for both normal and
contingency system operation. Design and specification of 2 x 12MVAr, 1 x
6MVAr and 1 x 65MVAr 5th harmonic filters.
48.
Mimosa
Mine (Zimbabwe) – Phase III expansionComplete underground reticulation for the
new Phase III expansion, including initial feasibility design and costing
for budget purposes, detailed design, specification and full project
management. Project included nine 11 kV/550V skid mounted substations,
surface compressor house and fans, electrical supply to main conveyor and
primary crusher.Project completion – 3rd quarter 2002
49.
Driefontein
Mine – No.1 Shaft EastComprehensive system study of the capability
of the existing 6,6 kV supply arrangement to provide an adequate capacity
for existing and future mine loading.
Recommendations in respect of remedial measures for, and
improvements to, the 6,6 kV supply, in order to ensure the network has
sufficient capacity to provide an adequate electrical supply for the future
load requirements. Comprehensive fault level and Protection Coordination
study in order to verify switchgear, cable ratings and protection
grading. Recommendations in respect
of improvements to the 6,6 kV supply arrangement.
50.
Western Platinum – Karee Mine Measurement
survey of the existing steady state and transient conditions at the 33 kV
supply.
51.
Harmony Gold Mine System
evaluation of the effectiveness of existing 6,6 kV PFC. Recommendations in
respect of PFC optimisation and project price for implementation of the
proposed recommendations.
52.
Driefontein Mine – No.5 Shaft East Comprehensive
fault level study in order to verify switchgear and cable ratings.
Recommendations in respect of improvements to the 6,6 kV supply
arrangement.
53.
Harmony Gold Mine Project
management – Optimisation of existing PFC banks as recommended in our
previous study.
54.
Anglo Platinum – Modikwa Mine Design,
specification, and project management of 33 kV PFC and harmonic filter
installation: 6 + 12 MVAr 5th harmonic filter banks.
55.
Anglo Platinum – Waterval Smelter Comprehensive
fault level study in order to verify switchgear and cable ratings.
Recommendations in respect of improvements to the 6,6 kV supply
arrangement.
56.
Amandelbult Mine Load
flow analysis of the existing steady state and transient conditions of the electrical
network and provide recommendations for additional predetermined loadings.
57.
Kloof Mine - 7 Shaft Comprehensive
fault level and protection device coordination study in order to verify
switchgear and cable ratings. Provide protection settings giving optimum
grading.
58.
Harmony - Doornkop Shaft Comprehensive
system study of the capability of the existing 6,6 kV supply arrangement to
provide an adequate capacity for existing and future mine loading.
Recommendations in respect of remedial measures for, and improvements to,
the 6,6 kV supply, in order to ensure the network has sufficient capacity
to provide an adequate electrical supply for the future load requirements.
Comprehensive fault level and protection coordination study in order to
verify switchgear, cable ratings and protection grading. Recommendations in
respect of improvements to the 6,6 kV supply arrangement.
59.
ARM Gold Mine System
evaluation of the effectiveness of existing 6,6 kV PFC. Recommendations in
respect of PFC optimisation and project price for implementation of the
proposed recommendations.
60.
Harmony Gold Mine – JoelPFC
optimisation study and implementation of our recommendations.
61.
Kumba Resources – Thabazimbi System
study, design and specification of 22 kV harmonic filter installation.
62.
Northam Platinum Comprehensive
system study and audit of the existing PFC design, in order to determine
load patterns and power factor and to reconfigure the PFC to suit the
Megaflex tariff.
63.
Kloof 5 Comprehensive
fault level and protection device coordination study in order to verify
switchgear and cable ratings. Provide protection settings giving optimum
grading.
64.
Driefontein 5 W PFC
optimisation study and implementation of our recommendations.
65.
Driefontein 2 E Comprehensive
fault level and protection device coordination study in order to verify
switchgear and cable ratings. Provide protection settings giving optimum
grading.
66.
Avmin – Beeshoek Mine PFC
optimisation study and implementation of our recommendations. Comprehensive
fault level and protection device coordination study.
67.
Avmin – Beeshoek Mine PFC
optimisation study and implementation of our recommendations. Comprehensive
fault level and protection device coordination study.
68.
Harmony Gold Mine Comprehensive
audit and recommendations of various PFC banks in the Harmony group.
69.
Amandelbult Mine Compilation
of complete MV electrical network into electronic format, to facilitate
future system planning and studies.
70.
Avmin – Beeshoek Mine Appointed
as client’s consultant to carry out necessary QA/QC of substation project.
71.
Tati Nickel – Botswana Comprehensive
electrical system study including, database compilation, PFC, load flow and
fault level studies, of the 11KV network.
72.
EHL – Western Limb Tailings Design,
specification, and project management of 6.6kV harmonic filter
installation: 2 x 5 MVAr 5th harmonic filter banks.
73.
Anglo Platinum – Polokwane smelter Inspection
and report of the installed furnace transformers.
74.
EHL – Boschfontein W. Mine Design,
specification and project management of 11 kV PFC and harmonic filter
installation.
75.
Assmang – Beeshoek Mine Design,
specification and project management of 22/11 KV PFC at South Mine.
76. Assmang – Black Rock Mine Comprehensive load flow, power factor
correction, fault level and protection coordination studies on the 22 kV
and 11 kV networks.
77. Driefontein 8 Comprehensive fault level and protection device coordination
study.
78. Harmony Masimong 5 Fault level and
protection device coordination study.
79. Driefontein 1 On site measurements,
PFC optimisation study and reconfiguration of existing PFC to our
recommendations.
80. DRD Blyvooruitzicht and Doornfontein On site measurements and PFC optimisation
study.
81. Anglo Platinum Amandelbult Database, fault level (including equipment rating
verification) and protection device coordination study of entire mine.
82. Harmony Gold Mining PFC audit on various mines.
83. Goldfields Beatrix 3 and 4 On site measurements and PFC optimisation study including
design of new PFC.
84. Harmony Phakisa Investigation into harmonic problems associated with existing
PFC and design of new PFC. Problems resolved at no capital cost.
85. Harmony Evander 2 and 7 On
site measurements and PFC optimisation study.
86. Goldfields Driefontein 1 Load flow study, protection device coordination study and
motor protection settings.
87. Harmony Lorraine Protection device coordination study.
88. Anglo Platinum Frank
Concentrator Earthing study.
89. Goldfields Kloof Main On site measurements, QOS study and investigation into motor
failure.
90. Anglo Platinum Union Database, fault level (including equipment rating
verification) and protection device coordination study of entire mine.
91. Goldfields Driefontein North Shaft Fault level and protection device coordination study.
92. Xstrata Coal South Witbank
Colliery PFC optimisation study.
93. Xstrata Coal Tavistock
Colliery PFC optimisation study.
94. Elandsrand Gold Mine Investigation into tripping of winders/ QOS study.
95. Doornkop Gold Mine Volt drop study.
96. Xstrata Coal Atcom Colliery PFC optimisation study.
97. Elandsrand Gold Mine Volt drop study.
98. Xstrata Coal Boschmans
Colliery PFC optimisation study.
99. Xstrata Coal Witcons Plant PFC optimisation study.
100.Xstrata Coal Waterpan
Colliery PFC optimisation study.
101.Konkola Copper Mine Comprehensive on site
measurements, load flow study, fault level study, PFC/harmonic study,
design and specification of 11kV PFC/harmonic filtering requirements.
102.Mopani
Copper Mine Comprehensive
on site measurements, load flow study, fault level study, PFC/harmonic
study, design and specification of 11kV PFC/harmonic filtering requirements
INDUSTRY
103.Eikenhof
pump station (Rand Water) Megaflex tariff impact
study. Electrical system study, PFC design, specification and project management
: 1 x 11 kV 5 MVAr 5th harmonic filter; 4 x 11 kV 890 kVAr unit capacitor
banks; 4 x 11 kV 710 kVAr unit capacitor banks.
104.Zwartkopjes
pump station (Rand Water) Megaflex tariff impact
study. Electrical system study, PFC design, specification and project
management : 15 x 6,6 kV 260 kVAr unit capacitor banks; 4 x 6,6 kV 470
kVAr unit capacitor banks; 2 x 6,6 kV 350 kVAr unit capacitor banks.
105.Houtkop
pump station (Rand Water) Megaflex tariff impact
study. Electrical system study, PFC design, specification and project
management : 7 x 2,2 kV and 3,3 kV unit capacitor banks.
106.Bandag
Alrode Project management : 1 x 6,6 kV 1,8 MVAr 5th harmonic
filter bank.
107.SAB
Pietersburg Project management : 1 x 11 kV 1 MVAr power factor
correction bank.
108.Transwerk
Koedoespoort Project management and equipment supply : revamp of two 11
kV blocking reactor bays, including supply and installation of 3 x 3,98
mH, 800 A blocking reactors, CTs and PILC terminations.
109.Lorne
Stewart (UK) Acceptance testing of dealing room on behalf of Lorne
Stewart, including fire control system, security system, UPS and
generator, air conditioning system and electrical services.
110.Daleside
substation (Rand Water) Evaluation of feasibility
of proposed 88/11 kV 20 MVA substation for Daleside pump station.
111.Vereeniging
pump station (Rand Water) Investigation to determine
possible causes for spurious tripping of slip ring recovery variable
speed drive harmonic filters.
112.Zuikerbosch
pump station (Rand Water) Megaflex tariff impact
study. Electrical system study, PFC design, specification and project
management : 70 x 6,6 / 11 kV unit capacitor banks; 6 x 11 kV 2 MVAr
damped 5th harmonic filters.
113.Palmiet
pump station (Rand Water) Megaflex tariff impact study.
Electrical system study, PFC design, specification and project management
: 32 x 11 kV unit capacitor banks; 2 x 11 kV 2 MVAr damped 5th harmonic
filters.
114.Lethabo
pump station (Rand Water) Electrical system study in
respect of additional 11 kV PFC / harmonic filtering requirements,
together with recommendations to optimise the existing installation.
115.Libanon
pump station (Rand Water) Megaflex tariff impact
study. Electrical system study, PFC design and specification.
116.Bloemendal
pump station (Rand Water) Megaflex tariff impact study.
Electrical system study, PFC design and specification.
117.Feralloys
Machadodorp Plant Electrical system study in respect of
the Plant 33 kV PFC requirements, following the planned upgrade of
Furnace 2, 3 and 5 from 24 MVA to 30 MVA.
118.Feralloys
Cato Ridge Plant Electrical system study in respect of
the effectiveness of existing 33 kV power factor correction and harmonic
filtering, together with the feasibility of converting the Furnace 1 and
2 supply to the Megaflex tariff.
119.Daleside
substation (Rand Water) Design and specification
for the complete 88/11 kV substation.
120.BMW
(SA) Rosslyn Electrical system study, PFC design and specification,
project management : 1 x 11kV 2,2 MVAr 5th harmonic filter and 1 x 11 kV
2,1 MVAr capacitor bank.
121.Feralloys
Machadodorp Plant
Electrical system study and project management in respect of 33 kV
power factor correction and harmonic filtering requirements for the
overall Plant, following installation of the new 54 MVA Furnace 1,
Sintering and Smelting plant loads.
|
|

|
122.Vametco
Minerals
Nightsave kVA demand and Megaflex tariff impact studies, together with an
electrical system study to evaluate the PFC requirements for each tariff
option. Recommendations in respect of tariff and PFC.
123.Polifin
Midland Plant (Sasolburg) Evaluation of the existing
33 kV supply harmonic conditions and effectiveness of existing
PFC/harmonic filters. Recommendations in respect of the rectifier
transformer phase shift required for the new 12 MVA rectiformer in order
to limit the harmonic impact of the new load. Determination of the
predicted plant load and power factor, harmonic conditions and filter
loading following installation of the new rectiformer.
124.SA
CHROME Comprehensive electrical system study for the overall new
project, including load flow and fault level studies, harmonic filter
design and specification.
125.Zimasco
(Zimbabwe)
Electrical system study in respect of the Plant 11 kV PFC
requirements following the planned furnace upgrades, and implications in
respect of harmonic conditions and loading of existing harmonic filters.
126.Lafarge
Cement (Lightenburg) Electrical system study in respect of
the Plant 11 kV and 3,3 kV PFC requirements on the Megaflex tariff,
design and specification of PFC/harmonic filters required. Project
management; 3MVAr and 2MVAr 6,6 kV 5th harmonic filters; 2MVAr and
3,5MVAr 3,3 kV 5th harmonic filters.
127.Anglo
Platinum – Frank Concentrator Determination of the
existing plant 6,6 kV load demand and power factor during typical
operation. Fault level study and protection coordination on the
substation incomers and main feeders.
128.Samancor
– Ferrochrome Quality Of Supply, earth resistance test and comprehensive
electrical system study in respect of 33 kV system supply capacity
requirements for the overall Plant, following the planned phased upgrade
and installation of a new sub-plant.
129.August
Lapple Electrical system study in respect of 11 kV PFC / harmonic
filtering requirements and project management.
130.SA
Chrome Fault finding on furnace current electrode measuring
system.
131.Ferrometals Plant –
Witbank Comprehensive electrical system study in respect of 33 kV system supply
capacity and power factor correction/harmonic filtering requirements for
the overall Plant, following the planned phased upgrade of the existing
48MVA Furnace 4 and Furnace 5 to 63MVA.
132.Anglo Platinum – ACP and Oxygen
PlantGreenfield study : Determination of the predicted plant load demand
and power factor during typical operation. Design, specification and
project management of required 6,6 kV PFC/harmonic filters to correct for
the plant load and to provide the required harmonic control
133.SA Chrome Investigation into catastrophic
failure of PFC filter bank. Recommendations and repair of bank, including
fitting of ‘bird’ protection.
134.Zwartkopjes
Pump Station (Rand Water) System
study, PFC design, specification supply and project management : 15 x 11
kV unit capacitor banks
135.Botswana Metal Refinery - Tati Activox Project System study,
PFC/harmonic filter design and specification of 3 x 11kV 4,5MVAr second
order damped 5th harmonic filters and 3 x 11kV 3,5MVAr 7th
harmonic filters. Project subsequently postponed.
136.Transnet PE Manganese Load flow study.
CITY COUNCILS & MUNICIPALITIES
137.Randfontein
TLC
Megaflex tariff impact study. Presentation of findings to Council.
Implementation of tariff conversion and assessment of actual savings.
138.Brakpan
TLC Standardrate tariff impact study. Electrical system study,
PFC design and specification, project management : 1 x 33 kV 9 MVAr 5th
harmonic filter.
|
|

|
139.Piet Retief Municipality Tariff
impact and PFC feasibility study.
140.Midrand Metropolitan Town
Council Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings. Electrical system study to evaluate the effectiveness of
existing 11 kV and 6,6 kV PFC installed, together with recommendations in
respect of PFC optimisation.
141.Local
Council of Krugersdorp Megaflex tariff impact study.
Presentation of findings to Council. Implementation of tariff conversion
and assessment of actual savings. Electrical system study to evaluate the
effectiveness of existing 11 kV and 6,6 kV PFC installed, together with
recommendations in respect of PFC optimisation.
142.Parys Town
Council Electrical system study, PFC design and specification,
project management : 1 x 11 kV 3 MVAr capacitor bank.
143.Pietersburg
TLC Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings. Electrical system study to evaluate the effectiveness of
existing 11 kV PFC installed, together with recommendations in respect of
PFC optimisation.
144.Kriel
TLC Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings.
145.Brakpan
TLC Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings.
146.Robertson
TLC Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings.
147.Volksrust
Local Council Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings.
148.Vryburg Town
Council Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings.
149.Delmas
TLC Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings.
150.Utrecht TLC
Megaflex tariff impact study. Presentation of findings to Council.
Implementation of tariff conversion and assessment of actual savings.
151.Glencoe
TLC Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings.
152.Groblersdal
TLC Megaflex tariff impact study. Presentation of findings to
Council. Implementation of tariff conversion and assessment of actual
savings.
153.City
Power Comprehensive study, design and recommendation
specification of 88 kV PFC and harmonic filter installation: 150 MVAr harmonic
filter banks.
154.Lephalale Municipality
Tariff conversion impact study, including power factor correction
analysis. Presentation of findings to Council. Implementation of tariff
conversion and assessment of actual savings. Nelspruit Town
Council Maintenance and repairs to the existing 33 kV Filter banks.
155.Lephalale Municipality Tariff
conversion impact study, including power factor correction analysis.
Presentation of findings to Council. Implementation of tariff conversion
and assessment of actual savings.
|
|
Top of Page
|