Redwing Technologies
REDWING TECHNOLOGIES






 

NEWS

 

 


 

BRAKPAN SIGNIFICANTLY REDUCES ELECTRICITY COSTS
by
Jeremy Hayward Pr.Eng


 

 

Through unique financing of new power factor correction equipment and tariff changeover, Brakpan Town Council have reduced their monthly electricity revenue with no financial outlay or risk by the Council.

Based on the results of a system study conducted by Redwing Technologies (Pty) Ltd for Brakpan Town Council, 9000 kVAr of power factor correction (PFC) has recently been installed at Brakpan's main intake electrical substation, with Redwing Technologies appointed as Project Consultants.

The interesting features of this Project were:

  • Due to an existing tariff metering agreement between Brakpan, Eskom and a major mining operation in the area, this project had to be carried out and completed in parallel, although independently, with a similar PFC project for the mining operation.

This PFC project for the mining operation was also carried out by Redwing Technologies, involving eight new harmonic filter/capacitor banks with a total output of 24 000 kVAr.

  • After successful commissioning of the 33 kV PFC in April 1999, Brakpan changed over to the Nightsave kVA demand tariff in order to realise projected savings of R500 000 in the present financial year, increasing to R2 300 000 in the 2000/2001 financial year.

Note that these savings include all project costs incurred by the Council.

  • The order for the PFC equipment was placed on Westingcorp Power Economy (WPE) based on their Self Finance Project format, whereby all equipment was supplied, installed and commissioned by the Contractor at no cost to the Council. Costs incurred by the Contractor are recovered after tariff changeover by the Council, through proven savings achieved on the monthly Eskom account.

The major benefits of the finance scheme offered by WPE were:

1.       there was no financial risk or capital outlay by the Council;

2.       if actual savings are lower than predicted due to an incorrect system analysis and/or equipment design by Redwing Technologies, or due to faulty equipment installed by the Contractor, costs recovered by the Contractor would also be reduced accordingly;

3.       the Contractor is responsible for all maintenance, insurance and operation of the PFC equipment for the duration of the payment period, with a 12-month guarantee period coming into effect after this.

  • A "fuseless" capacitor bank design was used which eliminates the unreliability problems associated with capacitor fusing, whether internal or external, thereby increasing the bank reliability. A critical factor on the kVA demand tariff, when unavailability of the capacitor bank for only 30-minutes could either significantly reduce or totally eliminate potential savings for that metering month.
  • The PFC bank was installed as a de-tuned capacitor bank (or harmonic filter), in order to eliminate potential consumer disruptions and/or "nuisance" tripping due to capacitor switching transients, and to avoid unacceptable amplification of prevailing system harmonics.

Harmonic filter
Installed 33 kV harmonic filter

The system study was submitted to the Council in August 1998, with the project order placed on WPE in October 1998 and completed in April 1999.

Now that Brakpan have optimised their electricity costs on the Eskom Standard tariff structure, Redwing Technologies are presently investigating the feasibility of further changing the Brakpan tariff to the time-of-use Megaflex tariff, in order to further maximise savings in monthly electricity revenue achieved by the Council.

This ongoing tariff project is an example of how pro-active tariff management can significantly reduce the monthly revenue of an electricity distributor, without incurring any capital expenses or financial risk to the distributor. The associated savings achieved can then be used to finance new Council projects, realising increasing living standards and economic growth in the area.



THIS DOCUMENT CONTAINS PROPRIETARY INFORMATION EXCLUSIVE TO REDWING TECHNOLOGIES (PTY) LTD. COPYRIGHT THEREFORE SUBSISTS IN THIS MATERIAL AND IT MAY NOT BE COPIED, OR TRANSFERRED TO A THIRD PARTY WITHOUT THE PRIOR WRITTEN CONSENT OF REDWING TECHNOLOGIES (PTY) LTD



Top of Page